On August 8/24/2020, the Shalda Creek diversion was closed. That created a back up on the creek which caused the LTL level to go up slightly. The contractor started opening the diversion wall on 8/24. They started with a small upstream removal and today are removing the downstream wall. The creek should be running through the new bridge today. The contractor expects all work to be done by September 4, 2020.