Inlet of new culvert
Coffer dam filled in
New culvert looking north
Culvert outlet
On August 8/24/2020, the Shalda Creek diversion was closed. That created a back up on the creek which caused the LTL level to go up slightly. The contractor started opening the diversion wall on 8/24. They started with a small upstream removal and today are removing the downstream wall. The creek should be running through the new bridge today. The contractor expects all work to be done by September 4, 2020.
A white boat bumper washed up at the Race's. It is label ABR#1 and SKI#1. Contact krace@gmail.com to claim.
Because the Zoom meeting on Saturday August 8 with Freshwater Solutions was cut short due to a power outage, it will be completed this upcoming Saturday. |